February 21, 2020

Using project management principles to hardwire ERAS protocols

By: OR Manager
Share

Implementation of Enhanced Recovery After Surgery (ERAS) at Virginia Commonwealth University (VCU) Health System in Richmond has been achieved through project and change management tools that transform the current state to the desired future state. To hardwire ERAS protocols in the OR as well as the ambulatory and acute care settings, we had to create a project team, identify our deliverables, develop tasks, and provide support for follow-through. The steps described in this article could serve as a primer for any project, but we apply them specifically to ERAS.

The Project Management Institute (PMI) defines a project as “…a temporary endeavor undertaken to create a unique product, service or result…Projects are temporary, but their deliverables may exist beyond the end of the project.”1 The key project management tools we used for our ERAS protocols were a sponsor, a charter, a work breakdown structure and task list, and a change management plan.

PMI’s definition of a sponsor is “a person or group who provides resources and support for the project, program, or portfolio and is accountable for enabling success.”1 An engaged sponsor provides project resources and helps remove barriers by serving as an advocate for the project with peers.

 

Normothermia interventions

To implement our normothermia interventions, we identified a group sponsor that included executive leadership from administration, anesthesiology, and nursing. Through ERAS, normothermia interventions were standardized to provide consistent surgical patient care, as follows:

• Interventions begin when a patient’s temperature drops below 36°C; monitoring of temperature standardized with a forehead temperature monitoring device that traveled with the patient throughout each phase of surgery.

• Passive and active warming beginning in the presurgical unit and ending when the patient leaves the postanesthesia care unit. Interventions include both cotton blankets and forced-air warmers.

• Patients transported with both passive and active warming.

• Patients receive warmed IV fluids.

• OR ambient temperatures are between 20°C and 25°C.

The project charter defines what work will and will not be performed. Our normothermia interventions included both the types of patients (over 18 undergoing surgical procedures) and what took place in each perioperative area.

The charter document often includes the business need and objective. It should be clearly written, as specific as possible, and free of jargon. When combined with additional overview information—such as any key performance indicators/goals, deliverables, preliminary key milestones, and project team members—this document provides a useful snapshot of the project and a reminder of expectations.

Once a charter is defined and approved by the project team, customers, and sponsors, it can be used as a touchstone for evaluating any proposed new deliverables and whether they will help achieve the objectives. By establishing a charter and deciding which elements should or should not be included in the project, the team has a much greater chance of success.

For the ERAS implementation of normothermia interventions, the charter included as the scope all perioperative care areas at the beginning of the project, but did not identify differences in the ambulatory surgery location and the main OR. Therefore, the intervention algorithm deliverable had to be reworked to reflect those differences, particularly in the timing of interventions.

 

Importance of stakeholders

For our ERAS implementation, we identified all stakeholders likely to be affected by the specific projects and sought their participation. Implementation of normothermia perioperative protocols and tools included representation from nursing, physicians, other clinical areas, and nonclinical roles.

It is important to consider the end-to-end process when identifying stakeholders and determining project team members. Project deliverables can have unintended consequences to those upstream or downstream from the specific deliverable, and having a multidisciplinary team involved in the work helps to mitigate potential pitfalls.

It’s important to identify not only the stakeholders who are advocates for the work but also those who might negatively impact the project so that the team can proactively manage potential conflicts.

To implement ERAS protocols associated with normothermia in the preoperative, intraoperative, and postoperative phases of care, a team consisting of providers, nursing staff, and equipment managers was formed to ensure effective deployment of the protocols and equipment. Each group brought unique questions reflecting their disciplines, and also communicated pending changes with their colleagues.

However, one lesson learned from the normothermia intervention was that differences between locations were not identified at the appropriate time because stakeholders representing the ambulatory surgical environment were not present during the development of the interventions.

The work breakdown structure allows the team to identify project deliverables and facilitates discussion of the steps needed to produce the deliverables. Once those steps are identified, they can be assigned to the responsible parties with deadlines for completion. A task list can be created and shared with the team. The team should regularly review and provide updates for each task to ensure accountability and keep the project moving forward.

 

Change management

Change management, as defined by Prosci, an organization that specializes in change management, is: “the process, tools, and techniques to manage the people side of change to achieve a required business outcome.”2

Change management tools ensure that not only are the project deliverables created but the people who will interact with those deliverables are prepared. According to Prosci’s Best Practices in Change Management, “with excellent change management…[a] project is six times more likely to meet objectives than with poor change management. Even fair change management is worth pursuing because you’re three times more likely to meet objectives.”3

Change management tools focus on how the work may impact the stakeholder group and inform the way training and communication plans are developed. Communication plans should include both project-related communications—ie, the status, risks, and issues that the sponsor or others should be aware of—and change communication.

Change communication helps those impacted by the project understand the value of the work (the “what’s in it for me?”), what the project means to their individual role, and how to be successful in the future.

Project team members are often selected because of their particular expertise or role in the organization, and they also can take on additional roles and responsibilities. It is important to set expectations for communication so that team members will share project information with their colleagues and bring questions and feedback from those colleagues to the project team.

 

Helpful tools

• Tracking lists.Three primary lists used in projects include issues, risks, and action items. The key difference between an issue and a risk is whether it has occurred. Issues are items actively affecting the project, whereas risks are things that could affect the project but have not occurred yet. Action items may include assigning responsibility, scheduling a meeting, or researching additional clinical evidence.

These lists help ensure details are not forgotten, and clarify who is responsible for resolving issues. Lists can also be helpful in determining when something needs to be escalated to senior management for resolution.

• Meeting notes. These are essential to help recall discussions, document decisions made during the meeting, and track action items.

• Status updates.These provide leadership with insight into project progress and serve as a starting point for resolving issues that require leadership support.

 

Ensuring success

VCU Health combined project management and change management tools throughout the implementation of ERAS. For the normothermia interventions ERAS project, both tool sets ensured that staff understood the practice changes and had the appropriate skills to deliver the interventions.

Another key element in implementing new processes, tools, or interventions is reinforcement to ensure the change is sustained. In a subsequent article, we will review how data can be used to measure patient outcomes and compliance with new processes. ✥

References

1. PMBOK® Guide—Sixth Edition (2017) https://www.pmi.org/pmbok-guide-standards/foundational/pmbok.

 

2. https://www.prosci.com/resources/articles/change-management-definition.

 

3. Prosci Best Practices in Change Management—2018 Edition. https://www.prosci.com/resources/articles/change-management-best-practices.